Thursday, October 20, 2005

 

Landscaping began Monday, October 10, 2005

Monday, October 10th - Grading began. Home contractor had 30 loads (approx. 12 yards each) of fill dirt on site.










Tuesday, October 11th - Sprinkler installation begins. 90% complete at end of day.

Wednesday, October 12th - Sprinkers finished, 6 x 6 timbers set in place boarding garden and property line side of all remote tree/flower beds.

Thursday - Sunday - Watering to help settling happen before final grading.

Monday, October 17th - Concrete curbing is installed



















Tuesday, October 18th - Plants are delivered, placed and planted. 12 large rocks are placed in remote beds. Unusal coloring with lichens. Rocks are larger than they appear. For a natural look, 50-75% of the rock is underground. Additional plants arrive to help fill in some bare spots. Sod is delivered.

Wednesday, October 19th - Bark chips, potting soil for garden, timbers buried and fine grading take place. Sod installation begins at 4:30pm. Workers stay until 9pm working by tractor light. Approximately 75% of sod is installed.

Thursday, October 20th - Sod is finished, flower sod is installed in remote beds. Walkways and driveway is hosed clean. Pallets and misc. containers are removed. Viola! Instant yard!